Retracom Transportable Buildings has just delivered a Fire
Rated HV Switchroom to MPA Engineering who are the main electrical
subcontractors to Monadelphous as part of flood resilience works at Urban
Utilities Oxley Creek WTP (Water Treatment Plant).
The facility suffered $32 million worth of damage in the Brisbane
Floods of 2011 and forced part of the plant offline. A range of flood proofing
measures are being rolled out including raising electrical equipment, such as
switchboards, 30cm higher than the 2011 flood peak.
Industrial and residential
growth in the area also dictated a capacity increase from 53 million to 65
million litres of sewage a day.
The HV switchroom measured 15.5x5.5x3.9m externally and
because it was specified with a (2 hour FRL) or 120/120/120 fire rating level
the building was constructed using flameguard sandwich panel in combination
with various other fire certified elements. The total building tare weight was
nearing 22 tons and it will be fitted out insitu with approximately 8-9 tons of
switch gear and control equipment by MPA over coming weeks. Retracom had also previously
supplied a smaller modular fire rated digestor switchroom.

These kind of inventions are a gift by the engineers to the world. Because they are life saving products otherwise hundred of people die in floods.
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteOur efficient experts who provide paper editing and proofreading services maintain the credibility of your paper with their top-notch services. Hire our paper proofreaders. Our assignment help expert is known for handling every type of college assignments for students. With an extensive experience in assignment writing, we deliver premier assignments within the given deadline. Looking for my assignment help, we are here to assist you.
ReplyDeleteWhy hello there ?! Our company https://expertpaperwriter.com/essaywriter-org-review/ do advise you to give us as long as possible where you can though. Not only will this work out cheaper for you, but we also offer fourteen days for you to review your essay and request any changes.
ReplyDeleteFire-rated switchrooms are essential to flood resilience efforts because they guarantee the safety and continuity of electrical systems in sensitive areas. Well, seeking for the LinkedIn profile writing help company to maintain personal profile updated according to the latest trends.
ReplyDeleteRetracom Transportable Buildings has delivered a Fire Rated HV Switchroom to MPA Engineering, the main electrical subcontractors to Monadelphous, as part of essential flood resilience upgrades at the Urban Utilities Oxley Creek Water Treatment Plant. The facility previously suffered around $32 million in damage during the Brisbane floods of 2011, which led to parts of the plant being taken offline, prompting significant infrastructure improvements. As part of the resilience strategy, critical electrical equipment such as switchboards is being raised 30 cm above the previous flood peak level to reduce future risk, while increased demand in the region has also required a capacity expansion from 53 million to 65 million litres of sewage per day. The newly delivered HV switchroom, measuring 15.5 x 5.5 x 3.9 metres externally, was built to a 2-hour fire resistance level (120/120/120 FRL) using flameguard sandwich panels and other certified fire-rated materials, resulting in a total tare weight of nearly 22 tons, with an additional 8–9 tons of electrical switchgear to be installed on-site. Projects like this highlight the importance of engineered infrastructure solutions, and students studying similar technical topics often look for support tools such as make my assignment to better understand complex industrial case studies and reporting requirements.
ReplyDelete